Penetrations through existing walls

By - , Build 155

When a penetration is required through the cladding of an existing building, effective sealing and weatherproofing is more difficult than when a penetration is incorporated during construction.

Figure 2 Sealing a pipe flange to cladding.
Figure 2 Sealing a pipe flange to cladding.
Figure 1 Pipe penetration through an existing exterior wall.
Figure 3 Heat pump pipework installation into an existing house.

FOR NEW CONSTRUCTION, guidance on sealing and weatherproofing penetrations through external wall claddings is provided in the Acceptable Solution E2/AS1 to NZBC clause E2 External moisture.

Many things require new penetrations

Occasionally, a penetration may need to be made through an existing wall cladding. Examples include when installing a heat pump, clothes dryer or rangehood, new plumbing or drainage pipes or cabling for TV, phone or data. In these situations, effective sealing and weatherproofing are more difficult to achieve.

Proactively minimise the risk

Things can be done, however, to mitigate the risk of water and air leakage created by penetrations through existing wall claddings.

Removing cladding best but difficult

If possible, the best solution is to remove enough of the external cladding to be able to access and fully seal the wall underlay around the penetration in accordance with E2/AS1. This is often not feasible.

Back to top

Locate in sheltered position

When a penetration must be made through external wall cladding, locate the penetration where possible in a sheltered position such as:

  • immediately under or through the eaves
  • under a veranda or porch
  • on the sheltered side of the building.

If it is not possible to locate an outlet in a sheltered part of the building, the penetration should be protected by a cowl or shield. By reducing the amount of water passing over the penetration, the risk of water entering the opening is also reduced.

Back to top

Slope opening to the exterior

Drill upwards from the exterior when cutting a penetration through the exterior cladding so that any water that gets in the hole is able to drain out again (see Figure 1).

The CANZ publication CP 01:2014 Code of practice for weathertight concrete and concrete masonry construction recommends that a penetration through an external wall has a minimum downward slope of 1.5° to the exterior.

Figure 1 Pipe penetration through an existing exterior wall.

Back to top

Seal around pipe penetrations

Pipes through a penetration should be firmly fixed so the pipe does not move within the opening. Apply sealant over a PEF backing rod around the opening, cover with a flange and seal around the top two-thirds of the flange collar (see Figures 1 and 2). Do not apply sealant to the flange sleeve, as the sleeve will allow any water that gets past the flange to drain to the outside.

As well as protecting against water entry, the flange will also protect the sealant around the opening from UV radiation or weathering.

Seal around pipes or sleeves where they penetrate interior linings.

Figure 2 Sealing a pipe flange to cladding.

Back to top

Install cabling in a conduit

Cabling and other flexible materials may be subjected to wind movement. This is likely to cause any sealant around the opening to be damaged and eventually fail.

Installing all cabling and flexible material in a conduit when retrofitting through existing cladding means the conduit can be sealed and flanged in the same way as the rigid pipe penetration.

Where wires are not in a conduit:

  • drill upwards through the cladding
  • protect with an exterior deflector sealed to cladding.

Relocating meter boxes

If a meter box needs to be relocated to the outside of the building, rivet a 30 × 30 mm angle to all sides of the meter box, and flash over the angle along the top edge in a similar way to the solution shown in E2/AS1 Figure 68.

Alternatively, a relocated meter box may be installed behind a window panel so it is isolated completely from the weather.

Sometimes have to avoid penetrations

Avoid penetrations through a flat or low-pitched roof or deck as these are more difficult to waterproof. If a penetration is required, another location for the penetration should be found.

Retrofitting heat pump pipework

Figures 3(a)-(d) show the installation of heat pump pipework into an existing house. The penetration for the pipework through the external cladding is high on the external wall and is under a veranda.

The hole is filled with sealant around the pipework. The proprietary cover has sealant applied to the top edges while the bottom is left open to allow any water that may get in to drain out again.

Figure 3 Heat pump pipework installation into an existing house.

Back to top

Download the PDF

More articles about these topics

Articles are correct at the time of publication but may have since become outdated.

Figure 2 Sealing a pipe flange to cladding.
Figure 2 Sealing a pipe flange to cladding.
Figure 1 Pipe penetration through an existing exterior wall.
Figure 3 Heat pump pipework installation into an existing house.