In-line lean-to junction detail

By - , Build 166

The roof-to-wall junction detail where the side of a lean-to finishes in line with the main building is tricky. We work through some options.

Figure 3 Steps 6–8 – Roof to-wall junction for in-line lean-to.
Figure 1 Junction detail location.
Figure 2 Steps 1–5 – Roof to-wall junction for in-line lean-to.
Figure 4 Steps 9–12 – Roof to-wall junction for in-line lean-to.
Figure 5 Steps 13–16 – Roof to-wall junction for in-line lean-to.
Figure 6 A simpler option – a step at the lower wall junction means the barge simply butts to the wall at right angles

ACCEPTABLE SOLUTION E2/AS1 doesn’t include details for roof-to-wall junctions where the side of a lean-to finishes in line with the main building and the roof slopes away from the upper wall (Figure 1).

Figure 1 Junction detail location.

Sequencing for installation

Figures 2–5 illustrate the steps for the construction of the detail where a sheet cladding is installed over a drained and vented cavity.

Step 1 – Complete all wall and roof framing.

Step 2 – Install wall underlay to lower-level walls.

Step 3 – Lay roof underlay to lean-to roof turned up higher wall and down face of wall.

Step 4 – Fit cavity battens to continuous side wall. Set horizontal batten to suit location of horizontal timber trim and flashing.

Step 5 – Fit flexible flashing tape to the corner at top of lean-to and dress over cavity battens.

Figure 2 Steps 1–5 – Roof to-wall junction for in-line lean-to.

Step 6 – Install roofing to lean-to.

Step 7 – Install cladding to lower level.

Step 8 – Fix bargeboard to side of lean-to and the horizontal timber trim.

Figure 3 Steps 6–8 – Roof to-wall junction for in-line lean-to.

Step 9 – Barge flashing installed.

Step 10 – Fit horizontal flashing to cladding break

Step 11 – Install wall underlay to upper side wall. Lap over flashing upstand.

Step 12 – Begin cavity closure, battens and cladding to side wall but don’t complete to corner. Complete horizontal z flashing to side wall.

Figure 4 Steps 9–12 – Roof to-wall junction for in-line lean-to.

Step 13 – Install horizontal apron flashing.

Step 14 – Install fabricated corner flashing over apron, barge and horizontal break flashing.

Step 15 – Install wall underlay to upper return wall, lap over apron flashing upturn.

Step 16 – Complete cavity closures, cavity battens and cladding installation on upper wall.

Figure 5 Steps 13–16 – Roof to-wall junction for in-line lean-to.

Some specifics from E2/AS1

Specific requirements of Acceptable Solution E2/AS1 include that there must be:

  • a 75 mm minimum wall cladding cover over the upstand
  • a gap between the wall cladding and the roofing as per E2/AS1 Table 7
  • cover over the roofing as per E2/AS1 Table 7 depending on wind zone and roof pitch.

Option to make this detail easier

Figure 6 provides a step at the lower wall junction so that the barge simply butts to the wall at right angles.

Figure 6 A simpler option – a step at the lower wall junction means the barge simply butts to the wall at right angles

Download the PDF

More articles about these topics

Articles are correct at the time of publication but may have since become outdated.

Figure 3 Steps 6–8 – Roof to-wall junction for in-line lean-to.
Figure 1 Junction detail location.
Figure 2 Steps 1–5 – Roof to-wall junction for in-line lean-to.
Figure 4 Steps 9–12 – Roof to-wall junction for in-line lean-to.
Figure 5 Steps 13–16 – Roof to-wall junction for in-line lean-to.
Figure 6 A simpler option – a step at the lower wall junction means the barge simply butts to the wall at right angles

Advertisement

Advertisement